Understanding takeoffs
Quantity Takeoff Example: A Flooring Takeoff, Room by Room
September 2026 · 7 min read · Reviewed by the OptiView product team
Abstract definitions only go so far. Here is what a small commercial flooring takeoff actually looks like on paper — net areas, waste factors, order quantities and the counted items — using a fictional project, plus the checks a reviewer would run before relying on any of it.
The scenario
A 1,980 SF office tenant improvement, drawing set Revision B, addendum 1 acknowledged. Four areas: two offices in luxury vinyl tile, a corridor in sheet vinyl, and a break room in porcelain tile laid diagonally. Wall base throughout, six transitions where materials change. The takeoff author measured from the floor plan sheets and the finish schedule; the quantities below are what a reviewer would receive.
The takeoff sheet
| Area | Material | Net area | Waste factor | Order quantity |
|---|---|---|---|---|
| Room 101 — office | LVT, glue-down | 480 SF | 7% | 514 SF |
| Room 102 — office | LVT, glue-down | 460 SF | 7% | 492 SF |
| Corridor | Sheet vinyl, 12 ft roll | 620 SF | 10% | 682 SF |
| Break room | Porcelain tile, diagonal | 240 SF | 12% | 269 SF |
Linear and counted items ride alongside the areas: 420 LF of 4-inch wall base (net measured perimeter, ordered at 441 LF with a 5% allowance), six transition strips, and two outside-corner details at the corridor junction. Each line names its source sheet — A-101 for dimensions, A-601 for the finish schedule — so a reviewer can find the evidence without hunting.
How each line was derived
- Net area comes from the measured room polygon on the plan, less columns and casework footprints called out on A-101.
- Waste factor follows the material: 7% for straight-lay LVT, 10% for sheet vinyl where seams and roll width drive cuts, 12% for diagonal-set tile where every perimeter cut is angled.
- Order quantity is net area multiplied by one plus the waste factor, rounded up to a clean ordering unit.
- Sheet vinyl adds a roll-layout note: 12 ft roll width, seams planned along the corridor length to avoid cross-seams in the traffic path.
What a reviewer checks on this sheet
This is where the takeoff becomes a reviewed takeoff. A reviewer does not re-measure everything — they interrogate the sheet against its sources: that Revision B is actually the governing set and addendum 1 did not change the finish schedule; that Room 102 was not double-counted where plan sheets overlap; that the corridor material matches the schedule and not just “vinyl”; that the diagonal tile carries the higher waste factor the layout demands; and that the roll-layout note is consistent with the seam locations a competent installer would accept.
Anything that fails those checks becomes a finding with its evidence attached — “Break room waste factor is 7% but tile is diagonal-set per A-601; confirm allowance” — and comes back as a correction the reviewer verifies. Only then does a senior reviewer approve the sheet as the reviewed version.